constructrr
The Constructrr Podcast artwork for “40% Time Savings with Off-site Construction and Why you Should or Shouldn’t Do It - w/ Ryan E Smith”
Type
Audio podcast
Primary guest
With Ryan E Smith

40% Time Savings with Off-site Construction and Why you Should or Shouldn’t Do It - w/ Ryan E Smith

Listen to the episode

Off-Site Construction Has to Be an Early Project Decision

By Brittanie Campbell-Turner

Published on Constructrr

The promise of faster delivery makes off-site construction easy to notice. The hard part is knowing whether a project is actually ready for it.

That was the question behind my 2017 Constructrr podcast conversation with off-site construction researcher Ryan E. Smith. I asked why a property owner should consider moving part of a project into a factory. Ryan described real schedule advantages, but his answer moved quickly past the headline. Off-site construction changes when people join the conversation, how design choices are made, how manufacturers are selected, when money moves, and how owners verify progress. If a team waits until the design is mostly settled, it may be testing the method under the wrong conditions.

Start with the project, not the schedule promise

Ryan E. Smith called off-site construction “more than a product, it’s a process.” He explained that schedule was the most consistent benefit in the studies he had reviewed. Cost was less certain. Results ranged from improvement to no meaningful change, with a smaller number of projects showing an increase.

That difference matters. A schedule benefit cannot answer whether a particular building, site, budget, or team fits the method.

Ryan connected stronger fit to repeatable work and spaces where several trades normally compete for access, such as bathrooms, kitchens, and mechanical rooms. Factory production can let people work in parallel, but only when the scope and delivery plan support it. The method follows the project conditions. The project should not be forced to follow the headline.

Late conversion can make the method look like the problem

Ryan returned several times to timing. He said a major off-site decision made after design development could hurt cost and schedule. He also described advising a developer who wanted to convert an already designed project to modular construction even though the design team did not have that experience and the design had not been tested for fit.

A poor late conversion can leave the team believing the method failed when the project never gave it the conditions it needed.

Off-site construction changes the design questions. The team has to consider how a component will be produced, transported, inspected, and assembled. Ryan argued that manufacturers and designers need to work through those questions together early. That is difficult to do after the main design decisions have already hardened.

Factory control moves risk instead of erasing it

Moving work indoors can make labor, scope, and production conditions more repeatable. It can also shift risk into supplier dependence, earlier cash needs, pricing transparency, factory and site inspection, warranties, and owner visibility.

Ryan said lowest bid was not enough when one manufacturer could carry a large portion of the project. The team may need interviews, facility visits, insurance, bonding, and a clearer view of delivery capability. He also urged owners and contractors to ask for pricing they could understand and manage.

The owner’s view of progress changes too. A normal site walk may no longer show where production stands. Local inspectors may need a plan for work that will be closed inside an assembly before it arrives. The team has to resolve those issues and decide how evidence, responsibility, and review will work before production begins.

Start small, but treat the learning as reusable

Ryan E. Smith held two ideas together. Off-site construction is a long-term capability, and the first step should be bounded.

He described design information, supplier relationships, financing knowledge, procurement choices, and regulatory experience as investments that can carry into later projects. At the same time, he recommended starting with a suitable scope, testing the approach, and expanding only after the team understands the result.

If your team is considering off-site work, start with a repeatable scope that is still early enough to change. Bring the owner, designer, contractor, and likely manufacturer into the same review while the team can still decide how pricing, progress, and inspection will stay visible. An issue the group cannot answer yet is useful information about readiness.

The useful decision is not whether off-site construction sounds faster. It is whether the project can support the process that makes faster delivery possible.

Recording information

People, topics, and original sources for this recording and article.

Original show notesGuest links and notes from the original episode page.

Ryan E Smith, author of


He is also Professor of University of Utah in the College of Architecture and Planning

We discuss the value proposition of doing offsite construction, and who is the best suited to embark on doing offsite, and what they need to be thinking about.

Resources:


 

Companies you should be paying attention to that are doing off-site construction epically:

  • Urban 1 Builders in Vancouver
  • Gluck Plus - Architecture /Developer/ GC Company
  • Marriot Hotels is working with Girden Modular out of Boise, Idaho.
  • Citizen M hotels where modules coming from Poland
  • Vertical integration models for the housing industry
  • Katerra
  • Blueprint Robotics

You can find Ryan E Smith at:


Music By: Epic Music Supervision

Show Notes: Constructrr.com/ep37

At a glance

Original source and related links